Where the PDF and notes go in ServiceM8
What Formbench adds to ServiceM8: the PDF, photos, job diary notes, follow-up jobs and emails.
On this page
The PDF
- Completing a report attaches the PDF to the job's attachments, named with the form's PDF file name setting. A form can switch this off in its Actions tab (Update this job), unless it emails the report.
- Completing it again after reopening attaches the new PDF and archives the old one, so only the latest is active.
- Send it to your client from ServiceM8 as you would any attachment, or have the form email it (below).
Follow-up jobs, emails, badges and status
Each form's Actions tab sets what else happens when it's completed:
- Follow-up job: a new Quote or Work Order with the defects in its description, copied client and contact details, a checklist, the PDF and defect photos, quote line items from your price list, a task for the office, and a note on both jobs with the job numbers. It can go to a job queue or to the tech who did the report.
- Email: sent through ServiceM8 to the job contact, billing contact or property manager, with the PDF attached. It appears in the job diary.
- Badge: added to the job when defects were found.
- Status: the job can be marked Completed.
The tech sees the result of each one after completing. Anything that didn't work says why and can be retried. Retrying never makes a second follow-up job.
Photos and videos
Photos and videos upload to the job's attachments as they're taken, not just at the end. Marked-up photos upload with the original as well.
Job diary notes
| When | Note |
|---|---|
| Report completed | The form's own note (set in its Actions tab), for example "Rental Safety Inspection completed by Sam Taylor. Result: Fail (2 failed)." followed by "PDF attached: (file name)". No note if the form turns it off. |
| Completed again | The same note again for the new revision. |
| Follow-up job created | "Follow-up quote #1234 created by Formbench from the …" on this job, and "Quote created from job #1001 …" on the new one. |
| Report emailed | The email itself, as ServiceM8 records it. |
| Draft PDF attached | "… draft PDF attached by … (the report isn't finished yet)" |
| PDF re-attached | "… PDF re-attached by … (replaces the earlier copy)" |
| Offline draft linked | "Formbench: Sam Taylor linked an offline draft of the … to this job." |
| Work in progress | A summary of a working session, see below. |
Work in progress notes
When someone works on a form and leaves it, or stops for 15 minutes, Formbench adds one note for that session. It says who worked on which form and when, which sections, how many answers, photos and videos were added, and how many items are marked Fail so far. It ends with "Report saved, not completed yet." No note is added if nothing changed.